U.S. Dept. of Interior
correspondence with VDOT regarding I-73 DEIS
(includes Blue Ridge Parkway, Appalachian Trail,
and U.S. Fish and Wildlife comments)
February
6, 2001,
Memorandum of transmittal of the Dept. of
Interior's review comments on the I-73
DEIS from Mr. Willie R. Taylor, Director,
Office of Environmental Policy and
Compliance to Mr. Roberto
Fonseca-Martinez, Division Administrator,
FHWA.
February
23, 2001,
Memorandum of transmittal of Visual
Quality Technical Memorandum from Patsy
Napier, Transportation Engineer, VDOT to
Mr. Gary Johnson, BLRI and Mr. Don Owens,
ATPO.
March
13, 2001,
Memorandum requesting an on-site meeting
in Roanoke, Virginia to discuss build
option segments crossing the Blue Ridge
Parkway from Mr. Daniel Brown,
Superintendent-BLRI to Mr. Earl T. Robb,
State Environmental Administrator, VDOT.
April
12, 2001,
Memorandum transmitting the Blue Ridge
Parkway's preferences and conclusions on
potential I-73 crossings of the Parkway
from Mr. Daniel Brown,
Superintendent-BLRI to Mr. Earl T. Robb,
State Environmental Administrator, VDOT.
Pictures - Overpass Study Concept for
Segment 376, Build Options 2, 2a, and 2c,
Blue Ridge Parkway Milepost 116.9
|
United
States Department of the Interior
OFFICE OF THE SECRETARY
Washington, D.C. 20240
ER-00/849
FEB 0 6 2001
Mr. Roberto Fonseca-Martinez
Division Administrator
Federal Highway Administration
Post Office Box 10249
400 North 8th Street, Room 750
Richmond, Virginia 23240
Dear Mr. Fonseca-Martinez:
Thank you for the opportunity to review and
comment on the 1-73 Location Study Between
Roanoke and the North Carolina State Line
Commonwealth of Virginia Draft Environmental
Impact Statement (DEIS) and Draft Section 4(f)
Evaluation - FHWA-VA-EIS-NH-962-2 (004), State
Project: 0073-962-FO1, PEI0I.
We cannot at this time concur that there are no
feasible and prudent alternatives to this project
or that all possible planning has been (sic) done
to mitigate harm to Department of the Interior
(DOI) resources. Our concerns and comments are
detailed below.
PARK AND RECREATION RESOURCES
The National Park Service (NPS) has a number of
concerns with the document as currently presented
and our primary concern at this point is with the
failure of the Virginia Department of
Transportation (V DOT) officials to consult with
The Appalachian National Scenic Trail and the
Blue Ridge Parkway (BRP) during the last 12
months of this process. (Communications prior to
that 12 month period were generally excellent,
and we believe that a similar level of
coordination during the last 12 months would have
corrected many of the flaws in both the
preliminary draft and the subject DEIS.)
Accordingly, we would like to reiterate our
request for consultation by the Federal Highway
Administration (FHwA) and the VDOT with the
Appalachian National Scenic Trail and the BRP at
every juncture throughout the National
Environmental Policy Act process and Section 4(f)
consultation process.
We have the following comments to offer on the
DEIS. Comments for the Appalachian National
Scenic Trail and the BRP are presented under
separate sections of this correspondence.
APPALACHIAN NATIONAL
SCENIC TRAIL COMMENTS
Description of the
Appalachian National Scenic Trail and its
significance:
The description of the Appalachian National
Scenic Trail on page 3.5-13 should be changed to
reflect recent history. The Trail is no longer
located on private land. A more accurate first
paragraph under Section 3.5.3.1 would be:
Portions of the Appalachian National Scenic Trail
are located within the viewshed of the 1-73
Location Study. The Trail is a unit of our
National Park System, and our nation's premier
national long-distance hiking trail - a
continuous, marked, 75-year old. 2,167-mile
footpath that traverses the Appalachian Mountain
chain through 14 states from central Maine to
northern Georgia. The Trail is located almost
entirely on public lands administered by the NPS
and the U.S. Forest Service. The 15-mile section
of the Trail potentially affected by the proposed
project begins on Tinker Mountain west of 1-81,
continues under 1-81 north of Exit 150, ascends
Fulharts Knob, and continues in a northeasterly
direction along the ridgeline north of the Blue
Ridge Parkway. This section of the Appalachian
Trail (from Tinker Mountain to Blackhorse Gap) is
one of the more popular day-hike sections of the
Trail in Virginia. This section of the Trail,
which is located on both NPS and U.S. Forest
Service lands, also is noted for its frequent and
often dramatic vistas that overlook the rural
countryside north and east of Roanoke.
Impacts to Scenic Values along the
Appalachian National Scenic Trail:
As we indicated in our comments on the DEIS, the
most serious omission with the document is that
it contains little actual analysis of the
potential impacts to the scenic values that are
present along this section of the Appalachian
National Scenic Trail Furthermore, the
methodology used for analysis of impacts to
scenic values appears to be fundamentally flawed,
since it does not appear to accurately reflect
the impacts of the proposed project on important
national recreation resources like the
Appalachian National Scenic Trail. We believe
that the visual analysis should rely on a
welltstablished, scientifically based
methodology, such as the U.S. Forest Service's
Scenery Management System.
For example. the information contained in Tables
4.5-2 and 4.5-3 (on pages 4.5-2 and 4.5-3,
respectively) appears to indicate that the visual
impacts of constructing Segment 372 would be
"low," with a average score of
"-3.32." This conclusion appears to be
based on criteria that are in direct conflict
with the narrative discussion of impacts to the
BRP and Appalachian National Scenic Trail. These
two resources are nationally significant units of
the National Park System managed primarily for
their scenic values, yet the visual analysis
concludes that the potential visual impacts of
Options I and lA on Segment 372 (which would
require a significant road cut at the crossing of
the BRP and be visible from 55 to 60 percent of
the Appalachian Trail of the three-mile hike
between Fulhart's Knob and Route 11 and be
visible from a number of scenic vistas along the
Trail north of Fulharts Knob) are
"low." We question how this outcome is
possible.
Furthermore. as noted in our comments on the
Preliminary Draft, the visual resource analysis
as currently displayed has the effect of
canceling the adverse impacts on remote and
highly scenic areas by citing a corresponding
positive impact for future motorists on the
highway. If the approach used in the preliminary
document were taken to what seems to be its
logical extreme, the cumulative visual impacts of
putting a highway through a wilderness area would
correlate roughly with the cumulative visual
impacts of putting a highway through an urban
setting: the existing wilderness setting would
become an urban one for wilderness users, but
motorists on the new road would enjoy the view!
In short, we believe that the visual analysis
does not meet the minimum threshold for an
adequate analysis. It should be reworked using a
well-established, scientifically based
methodology, such as the U.S. Forest Service's
Scenery Management System.
Despite repeated requests in previous
correspondence. coordination meetings and field
reviews. we still have not been provided with
copies of visual simulations as promised by VDOT
representatives. As noted in our comments on the
DEIS, these simulations, plus a narrative
description of the visual impacts depicted in the
simulations, are essential components of the
analysis of impacts to scenic resources. We would
appreciate being provided with copies of these
simulations, as well as the written narrative
prepared by the consultant responsible for the
visual analysis as soon as possible.
Noise Impacts to the Appalachian National
Scenic Trail:
The analysis currently states that "noise
from 1-73 would dissipate to ambient or existing
levels and not impact the Appalachian
Trail." We believe that this is inaccurate.
NPS employees have recently hiked this section of
the Appalachian Trail, and found that traffic on
existing highways and county roads, construction
noise, and other sounds from the valley north of
Roanoke can be heard clearly along the
Appalachian Trail at Fulharts Knob and other
locations. The dominant sounds that would be
associated with the proposed northern route of
1-73 through this landscape - particularly the
sounds of the truck traffic - will be far more
apparent. Again, as noted in our previous
comments, the NPS has conducted extensive studies
of the effects of noise on visitor enjoyment in
parks. "Natural quiet is an important
component of many park experiences, and
particularly important to backcountry
recreational experiences like those found along
the Appalachian Trail. This concept needs to be
addressed in the noise analysis.
Moreover, the analysis of auditory impacts as
currently presented in the preliminary draft
seerns to be based on what people in a
residential or work environment are accustomed
to. In remote recreational areas, such as those
found along the Appalachian Trail, manmade sounds
are far more intrusive at low levels. In other
words, although the incremental difference in
sounds associated with the project may be as
little as 20 percent above background noise, if
the sound can be heard and recognized, it can
change a remote backcountry experience to a
developed recreational experience. To base
analysis of the auditory impacts to a backcountry
resource such as the Appalachian Trail on noise
levels found in residential and work environments
is inappropriate.
Impacts to the Recreational Experience
Provided by the Appalachian National Scenic
Trail:
Ultimately, changes in the visual and auditory
environment of the Appalachian Trail have the
potential to change the visitors' experiences
while on the Trail. If these visual and auditory
impacts are frequent. egregious, or inconsistent
with visitors' expectations, they can change a
remote recreational experience to one that is
more likely to occur in a developed setting. None
of these potential impacts is discussed in the
current draft.
Section 4 (f) and Future Coordination and
Consultation:
Lastly, we believe that the Appalachian National
Scenic Trail should be considered as a Section 4
(f) resource in the document, based on the
concept of constructive use. The proposed
northern route of I-73 has clear, measurable
impacts that affect the Appalachian Trail -
impacts that have not been fully or accurately
quantified in the DEIS. Perhaps the most
appropriate forum for discussing this issue would
be in a meeting attended by representatives from
the BRP, the Appalachian National Scenic Trail,
the Appalachian Trail Conference, the Roanoke
Appalachian Trail Club, and the Jefferson and
George Washington National Forests.
BLUE RIDGE PARKWAY COMMENTS
This section presents comments specific to the
five locations that build alternative options are
being considered for crossing of BRP land (see
the following table).
Build Alt.
Options |
Crossing Type |
Blue Ridge Parkway
Crossing Locations |
| 1 and 1a |
Underpass |
Segment 372 |
Milepost 103.6 |
Blue Ridge Community |
| 2, 2a and 2c |
Overpass |
Segment 376 |
Milepost 116.9 |
Mt. Pleasant Community |
| 2b, 3, 3b, and 3c |
Underpass |
Segment 118C |
Milepost 121.4 |
Existing US 220 Corridor |
| 3a |
Underpass |
Segment 105 |
Milepost 124.1 |
Back Creek Area |
| 4 |
Underpass |
Segment 371 |
Milepost 126.5 |
Mason's Knob Overlook |
Comments are based upon the review and evaluation
of data relevant to the five-Parkway crossings
discussed in CHAPTER 3.0 AFFECTED ENVIRONMENT and
CHAPTER 4.0 ENVIRONMENTAL CONSEQUENCES. While
this DEIS is more complete than the earlier
Preliminary DEIS. agency reviewers still found
that not all of the available data related to the
Parkway were included in the DEIS. Data that the
Service believes to be relevant to the evaluation
of proposed Parkway crossing segments are also
included as comments and in support of
conclusions reached by the NPS.
Preliminary Preferred Parkway Crossing
Conclusions:
The DEIS and supplemental data were used by the
NPS to evaluate the five alternative build option
segments and prioritize them in rank order from
most preferred to least preferred. The following
is a preliminary ranking of NPS preferences
pending the outcome of a future on-site meeting
in Roanoke, Virginia, being requested via this
comment transmittal. Based upon the results of
that meeting, the NPS will provide its final
preference conclusions within thirty days of the
on-site meeting.
Based upon current data, the NPS's most preferred
crossing of the BRP is segment 118C, Milepost
121.4 included in Build Alternative Options 2b,
3, 3b, and 3c. This is the existing four-lane
corridor of U.S. Route 220, a major
transportation corridor that has been a part of
the Parkway visitor driving experience since the
Parkway was constructed through the Roanoke
Valley during the late 1950's and early 1960's.
Widening of the U.S. 220 corridor to accommodate
1-73 will further impact this area of the Parkway
but the landscape changes would be more
consistent with existing land use than they would
be in the other four proposed Parkway crossing
locations.
Segment 105, Milepost 124.1 included in Build
Alternative Option 3a is the next most preferred
crossing location. Between Parkway Milepost 121.4
at U.S. Route 220 and Milepost 126.1 there are
four Virginia Secondary Route underpass crossings
of the Parkway. Proposed Segment 105 is located
within an existing underpass crossing of VA Route
615 and the Norfolk Southern Railroad. This is
the next most preferred crossing by the NPS
because this series of underpass structures is a
prirnary character-defining element of this 4.7 -
mile section of Parkway. While widening the
existing corridor with side-hill cuts to
accommodate a four-lane interstate would
dramatically change the landscape, those changes
would be more consistent with existing land uses
and site conditions than the other three
locations which are characterized by forest
covered slopes or rolling rural residential and
farmlands. However, from a natural resources
perspective, this is a less preferred option
because crossing here would result in extensive
forest fragmentation and loss of canopy
vegetation.
The remaining three segments--Segment 371,
Milepost 126.5; Segment 372, Milepost 103.6 and
Segment 376, Milepost 116.9 included in Build
Alternative Options 4; 1 and la; and 2, 2a and
2c, respectively are all less preferred options,
in our opinion. The construction of an interstate
highway in any of these three Parkway landscape
settings would dramatically change the existing
view area's scenic quality, and land uses, all of
which are absent of major roads seen from or
crossing the Parkway. Increases in highway noise
generated by interstate highway traffic volumes
and vehicle speed would radically alter existing
site noise conditions.
Segment 371, Milepost 126.5 is the southern most
proposed segment, characterized by forest cover
and is just south of Masons Knob Parking
Overlook, a paved parking area for 28 cars. Both
the existing land use and the proximity of
Segment 371 to a formal overlook parking area are
of great concern to the NPS. Noise increases,
land use changes and view area scenic quality
impacts form the basis for this being a least
preferred crossing option.
Segment 372, Milepost 103.6 is the northern most
proposed crossing of the Parkway. Between Parkway
Milepost 90 and 104 the Parkway traverses
primarily national forest land and the visitor
experience is dominated by a forested road
corridor with vistas of undeveloped forest lands.
From Milepost 104 to 105.8 land use is rural
residential with U.S. 460 crossing the Parkway at
Milepost 105.8. The introduction of another
four-lane highway, especially one meeting
interstate standards into this forest dominated
setting, greatly alters the existing visitor
experience. Again, increased noise, changes in
land use and view area scenic quality impacts
form the basis for this being a least preferred
crossing option.
Segment 376, Milepost 116.9 is in a section of
Parkway dominated by rural farm and residential
use. This portion of Parkway lies midway between
U.S. Route 24 and U.S. Route 220. Views of roads
in this area and within Parkway view areas are
inconsequential. The narrow secondary routes that
cross the Parkway do so under or over the Parkway
on picturesque stone arch bridges. These
structures are so well placed and their scale is
such that they enhance the overall driving
experience and do not dominate it. An interstate
highway constructed through this area would
overpower the current landscape setting with its
scale, mass and engineered character. Again
noise, land use changes and view area scenic
quality impacts are of great concern in this
location and make it a least preferred crossing
option.
The foregoing is a summary of NPS conclusions
based upon the following in-depth review and
evaluation of DEIS data.
General Blue Ridge Parkway Review
Comments:
While the NPS has reached preliminary conclusions
on the order of preference for the five proposed
Parkway crossings, there are additional data not
included in the DEIS that Parkway Resource
Planning staff would like to review. Therefore,
the NPS requests that the VDOT schedule an
on-site meeting in Roanoke, Virginia with Blue
Ridge Parkway Resource Planning staff, the FHWA
and appropriate DEIS consulting staff to review
affected visual environment and environmental
consequences data specific to the five segments
crossing the Parkway and their associated
landscape units. This meeting should be scheduled
as soon as possible so that the NPS's preference
for crossings can be finalized and transmitted to
VDOT prior to finalization of the EIS.
The meeting is being requested because there is
little definitive descriptive inventory and
assessment data included in the DElS supporting
conclusions and findings presented in the
EXECUTIVE SUMMARY. CHAPTER 3.0 AFFECTED
ENVIRONMENT OR CHAPTER 4.0 ENVIRONMENTAL
CONSEQUENCES sections related to the BRP. Agency
reviewers found it difficult to evaluate build
alternative options affecting the BRP given the
absence of affected environment and impact
assessment data supporting the DEIS.
Specific Blue Ridge Parkway Review
Comments:
The following comments are organized under
chapter and section headings used in the DEIS.
CHAPTER 3.0 AFFECTED ENVIRONMENT
3.5 VISUAL SETTING
3.5.1 AFFECTED ENVIRONMENT
3.5.1.1 Definition of Existing Visual Environment
Under this section there is a discussion of the
landscape classification system, definitions and
a general description of landscape regions and
districts. The next-to-the-last paragraph on page
3.5-1 in this section states that "Each
landscape district was further divided into
landscape units." In the last paragraph the
classification of landscape units is said to have
"..,considered topography, vegetation,
proximity to proposed alignments, close and
distant views, cultural landscape and land use,
landmarks, historic structures, views, and the
public's perception of visual importance. Special
features and issues of each unit were described
from a context of cultural, existing development,
local perceptions, and community concerns. The
variations of environment along the potential
corridor-urbanization, farmlands, suburban
development, parkland, etc. -were also recognized
through the landscape unit definitions."
Study process and types of data studied are
presented, yet there is no presentation of
inventory or assessment data that was gathered
for any of the landscape units. There is no
written or graphic description of the affected
visual environment or landscape units beyond the
methods used to identify, inventory and assess
them and maps showing their names and geographic
locations. These data that were not presented are
in fact the information that would define for the
reader/reviewer the visual environment affected
by the various 1-73 build alternative options.
3.5.1.2 Assessment of Existing Visual Ouality of
Landscape Units
Again this section discusses visual quality
definitions, evaluation criteria and visual
quality rating of landscape units, but includes
no discussion of what this process yielded in
terms of visual character or scenic quality data
for each option and/or segment landscape units.
Even some general description here would better
meet the intent of the affected environment
chapter to provide the reader/reviewer with an
understanding of what the visual setting is and
how it varies by option, segment location and
landscape unit. This information is necessary to
provide the basis for understanding the segment
impact ratings in CHAPTER 4.0 and to provide the
context for the next phases of "context
sensitive design."
3.5.1.3 Assessment of Views from the Blue Ridge
Parkway
There is no description of the BRP's visual
setting context or specific scenic attributes
that articulate its scenic character or
importance within the Roanoke Valley between
rnilepost 103 and 127. This 24 mile-long section
of Parkway establishes the resource context
within which to evaluate proposed crossings and
their relative visual impacts. There is no
description of view areas or individual landscape
unit assessment results presented in the DEIS.
The BRP planning staff made viewshed sensitivity
mapping, view area maps and scenic quality
assessment ratings for each view area for this
Parkway section available to the DEIS project
consultants to assist the DEIS team in their
describing the Parkway's affected visual
environment. Data provided by Parkway staff
should have enabled the Parkway to be treated at
two levels of detail - a general description of
the Parkway's visual character, visual
sensitivity and view areas' scenic quality
between milepost 103 and 127; and specific
treatment of these elements for each of the five
proposed segment crossings.
The lack of information in this section does not
create for the reader/reviewer an adequate mental
and visual image of what the Parkway looks like
or its scenic importance. Thus later in the
impact analysis there is no visual data
foundation for evaluating the relative impacts of
the various options.
3.5.2 ENVIRONMENTAL CONSEQUENCES
The second paragraph states, "The impact
analysis did not only consider direct impacts,
but also secondary' and cumulative impacts on the
visual quality." These data were not
presented in the Affected Environment or the
Environmental Consequences Chapters.
CHAPTER 4.0 ENVIRONMENTAL CONSEQUENCE
4.5 VISUAL QUALITY
4.5.4 Build Alternatives
4.5.4.2 Build Option 1 and 4.5.4.3 Build Option
la
Segment 372 is the portion of Build Option 1 and
1a that crosses the BRP at Milepost 103.6. In
Tables 4.5-2 OPTION 1 and 4.5-3 OPTION la VISUAL
IMPACT RATING Segment 372 is comprised of 19
landscape units. When combined, those units have
a "low" Visual Impact Rating. Segment
372 is one of the NPS's least preferred crossing
options because the landscape unit tha
encompasses this geographic area is comprised of
forested and adjacent rural land uses that are
currently unaffected by major transportation
corridors in the immediate area of the proposed
crossing. The introduction of an interstate
highway in this highly visually sensitive area
would cause a substantial adverse change and
therefore should be rated as having a substantial
adverse impact within this landscape unit. It is
the NPS's conclusion that this crossing would
have high visual impacts directly a Parkway land
resources and secondarily on view area scenic
quality rather than a low visual impact rating.
This alternative would also affect the
Appalachian National Scenic Trail's viewshed.
Additional discussion of NPS conclusions follow
below under Segment 372 BRP Evaluation comments.
4.5.4.4 Build Option 2, 4.5.4.5 Build Option 2a,
and 4.5.4.7 Build Option 2c
Segment 376 is the portion of Build Option 2, 2a,
and 2c that crosses the BRP at Milepost 116.9. In
Tables 4.5-4 OPTION 2,4.5-5 OPTION 2a and 4.5-7
OPTION 2c VISUAL IMPACT RATING Segment 376 is
comprised of 5 landscape units. When combined,
those units have a "medium" Visual
Impact Rating. The particular landscape unit that
encompasses this geographic area is comprised of
rural farm and residential land uses that are
currently unaffected by major transportation
corridors. The NPS reviewers concur with the
statements on pages 4.54 and 4.5-5 essentially
stating that this crossing would become a
dominant visual element in the landscape and have
high visual impacts directly on Parkway land
resources and secondarily on view area scenic
quality. Segment 376 is the second of three of
the NPS's least preferred crossing options
presented in the DEIS. It is the NPS's conclusion
that this crossing would have high visual impacts
directly on Parkway land resources and
secondarily on view area scenic quality rather
than the medium rating in Tables 4.54.4.5.5, and
4.5-7. Additional discussion of NPS conclusions
follow below under Segment 376 BRP Evaluation
comments.
4.5.4.6 Build Option 2b, 4.5.4.8 Build Option 3,
4.5.4.10 Build Option 3b and 4.5.4.11 Build
Option 3c
Segment 118C is the portion of Build Options 2b,
3, 3b, and 3c that crosses the BRP at Milepost
121.4. In Tables 4.5-6 OPTION 2b, 4.5-8 OPTION 3,
4.5-10 OPTION 3b and 4.5-11 OPTION 3c VISUAL
IMPACT RATING Segment 118C is comprised of 4
landscape units. When combined those units have a
"low" Visual Impact Rating. The
particular landscape unit that encompasses this
geographic area is comprised of rural residences,
agricultural lease lands, a major quarry
operation and the four-lane highway corridor of
U.S. Route 220. The NPS reviewers concur with the
statements on pages 4.5-6.8, and 10, that this
Segment 118C crossing would have a moderate to
high visual impact primarily for surrounding
homes. However, visual impacts to the Parkway
visitor experience in this landscape unit are
seen as being relatively low because this
location is already dominated by highly impacting
land uses including a quarry and a four-lane
highway. The existing U.S. Route 220 corridor is
a dominant visual element in the landscape and
has directly affected the visitor's experience of
the Parkway since the early 1960's. Additional
and larger cut slopes and highway structures will
impact the current landscape setting. but less so
here than the other proposed crossing locations.
The Segment 118C, by following the U.S. Route 220
corridor, would introduce less change in visual
quality by comparison to current land uses in
this location than at any of the other four
proposed crossings. Additional discussion of NPS
conclusions follow below under Segment 118C BRP
Evaluation comments.
4.5.4.9 Build Option 3a
Segment 105 is the portion of Build Option 3a
that crosses the BRP at Milepost 124.1. In Table
4.5-9 OPTION 3a VISUAL IMPACT RATING Segment 105
is comprised of 4 landscape units. When combined.
those units have a "low" Visual Impact
Rating. The landscape unit that encompasses this
geographic area is comprised of forested slopes,
a state secondary roadway, a railroad
right-of-way and rural residences. Within this
landscape unit there are four Virginia Secondary
Route underpass crossings of the Parkway between
Parkway Milepost 121.4 at U.S. Route 220 and
Milepost 126.1. Proposed Segment 105 is located
within one of the existing underpass crossings of
VA Route 615 and the Norfolk Southern Railroad.
This is the second most preferred crossing by the
NPS because this series of underpass structures
is a primary character-defining element of this
4.7 mile section of the Parkwav. While widening
the existing corridor with side-hill cuts to
accommodate a four-lane interstate would
dramatically change the landscape, those changes
would be more consistent with existing land uses
and site conditions than three of the other
crossing segments-371, 372 and 376. Additional
discussion of NPS conclusions follow below under
Segment 105 BRP Evaluation comments.
4.5.4.12 Build Option 4
Segment 371 is the portion of Build Option 4 that
crosses the BRP at Milepost 126.5. In Tables
4.5-12 OPTION 4 VISUAL IMPACT RATING Segment 371
is comprised of 18 landscape units. When
combined, those units have a "medium"
Visual Impact Rating. This geographic area and
its defining landscape unit is comprised of rural
farm and forested land uses that are currently
unaffected by major transportation corridors.
There are no definitive statements about the
visual quality or impact ratings for Segment 371
crossing the BRP. However, NPS reviewers believe
that this crossing would become a dominant visual
element in the landscape and have high visual
impacts directly on Parkway land resources and
secondarily on view area scenic quality. Segment
371 is the third of three of the NPS's least
preferred crossing options presented in the DEIS.
It is the NPS's conclusion that this crossing
would have high visual impacts directly on
Parkway land resources and secondarily on view
area scenic quality rather than the medium impact
rating shown in Table 4.5-12. Additional
discussion of NPS conclusions follow below under
Segment 371 BRP Evaluation comments.
4.5.5 Special Visual Concern Areas
4.5.5.2 Blue Ridge Parkway
General Notes
Under the "Qualitative Analysis portion of
the following five Segment Evaluation sections
the cell data could not be related to the legend
for visibility data displayed on Figure 4.5-1
VISIBILITY OF ALTERNATIVE CROSSINGS FROM THE BLUE
RIDGE PARKWAY. The contrast of the black to gray
scale of the legend did not reproduce with enough
clarity to distinguish the varying visibility of
the different crossings. Reviewers require
additional explanation of these data and a better
quality graphic.
Comments have been combined for the Segment and
Option Evaluation sections as a matter of
efficiency since these sections seem to be
somewhat repetitive.
Segment 105 and Option la BRP Evaluation
Qualitative Analysis:
The NPS reviewers agree with the DEIS conclusions
that this crossing would have moderate foreground
and high middle ground impacts. The DEIS
described impacts to the "cinematic
experience" are described as being
relatively low. This is a correct conclusion in
the NPS's opinion but because there is a series
of underpass structures through this 4.7-mile
section of the Parkway, they become a prinrary
character~efining element of the visitors'
cinematic experience. The sequential experience
is a series of transitions going from forested
slopes to bridge underpass structures. The
Segrnent 105 crossing would be wider than it
currently is and more noticeable than the other
underpass crossings in this specific area but it
would not alter the current pattern of visual
experience.
Segment 118C and Options 2b, 3, 3b and 3c BRP
Evaluation
Qualitative Analysis:
The NPS reviewers agree with the DEIS conclusions
that this crossing would have low foreground and
middle ground impacts and that the impact on the
cinematic experience would be moderate. Reviewers
are not sure how to interpret the meaning of the
DEIS statement, "The corridor would have its
own presence as an event in the choreographed
sequence, rather than just an edge between forest
and grassland field." If this means that it
will be more visible, and therefore must be well
designed and sited as it crosses the existing
Parkway landscape, then this would be agreed
with.
Segment 371 and Option 4 BRP Evaluation
Qualitative Analysis:
The analysis and conclusions of these sections
are well stated and express the NPS's conclusions
that this crossing would greatly affect the
existing Parkway landscape setting and would
cause maximum potential negative visual effects.
Segment 372 and Options 1 and 1a BRP Evaluation
Qualitative Analysis:
The NPS reviewers agree with the DEIS conclusions
that this crossing would also have a relatively
high impact on the foreground and cinematic
experience of the Parkway.
Segment 376 and Ontions 2, 2a and 2c BRP
Evaluation
Qualitative Analysis:
The NPS reviewers disagree with the visual impact
analysis findings included in the DEIS for the
Parkway foreground, middle ground and cinematic
experience for this crossing segment. This
crossing would be very obvious in the Parkway's
foreground and middle ground views. This is
especially the situation because this segment is
proposed to cross over the Parkway motor road,
not under it as proposed for the other four
crossings. This view area is incredibly visible
for southbound Parkway traffic because of the
current broad unobstructed vista off to the right
or southwest. A major bridge structure carrying
four lanes of traffic over the Parkway would
introduce a massive obstruction into what is now
a very open view area. This segment crossing lies
within Parkway Scenic Resource View Area RO-15
that was deterrnined by Parkway planning staff to
have a scenic quality rating of 11, or moderate
scenic quality. It is relatively intact as a
rural residential and farm land scene and is one
of the longer duration views in the Roanoke
Valley. Construction of 1-73 as described in the
DEIS would degrade the intactness and visual
integrity of this view are that it most certainly
would become one of the least scenic views in the
Roanoke Valley. The NPS characterize this view
area as having more importance than does the DEIS
data.
Because of the differences between the NPS and
the DEIS consultant staff conclusions, and this
crossing over the Parkway, this segment needs to
be discussed in much more detail at the requested
on-site meeting. Visual simulation of this
crossing would be most useful in evaluating
potential visual impacts. Please consider
preparing this for NPS reviewers to evaluate.
4.5.6 Mitigating Measures
This section does not present any specific
mitigating measures but there are statements
about VDOT's commitment to working with the NPS
to minimize impacts to the BRP once an
alternative is selected. The NPS is also
committed to that phase of the planning and
design process of the 1-73 project. Mitigating
measures are going to play a significant role in
maintaining the historical significance of the
Parkway's designed landscape and scenic view
areas.
4.7 NATURAL RESOURCES
The following comments are not organized under a
specific section but are presented by build
alternative options and segments.
Option 1 & la, Segment 372, Milepost 103.6
This site is located north of Route 460 in the
Ridge District and is the most northern crossing
and is a heavily forested site. It would require
extensive cut slopes and excavation. Much of the
canopy vegetation would be lost. Very little is
known by Parkway biologists about the ecology of
this site. Additional field review is needed by
Parkway Natural Resource Management staff and
VDOT for this option.
This is one of the least preferred options since
extensive forest fragmentation would occur if
crossings were constructed at this site.
Secondary impacts from adjacent development is
likely to occur. further impacting Parkway
resources.
Option 2, 2a, & 2c. Segment 376. Milepost
116.9
This segment would cross through 4 agricultural
leases (parcels IM-132, IM-134, IM-135 &
1M-136). There is a small spring/seep/wetland
located in lease IM-132. In addition, there is
rich cove forest, just north of MP 117. A small
stream (which originates from the spring/ seep),
flows through the forested area. There are
numerous large diameter at breast height (dbh)
oaks and maples within the wooded area. All of
the agricultural leases at this location are
highly visible from the Parkway.
This option is not preferred from a natural
resources perspective but would be acceptable.
This alternative would result in moderate impacts
to natural resources, but these sites are already
somewhat fragmented. If this is selected as the
preferred alternative, a more comprehensive
biological survey would be required.
Option 2b, 3, 3b. & 3c, Segment 118 C,
Milepost 121.4
This alternative uses the existing Route 220
corridor and interchange. There is one
agricultural lease (parcel IM-147) located on the
north side of Route 220. This 1-73 segment will
take the largest amount of BRP lands (approx.
8-acres). The existing access from Route 220 to
the Parkway would be eliminated under this
alternative. Approximately 1/3 of the
agricultural lease will be lost under this
alternative.
Under this alternative, new interchanges with the
Parkway are proposed using existing state roads,
but the DEIS does not really go into much detail
about these interchanges or how much land they
would impact.
Despite the fact that this alternative takes the
most amount of land from the Parkway, this is the
preferred alternative from a natural resource
perspective because it uses an already heavily
disturbed area--the existing U.S. Route 220
corridor.
The DEIS should be revised to include maps and
additional information on the alternatives for
the new interchange with the parkway. It is
difficult to judge the total impact to the
Parkway at this site without this additional
information.
Mitigating measures should insure that vegetation
which currently screens the Rocky Dale Quarry
from the Parkway is left intact.
Option 3a Sezment 105, Milepost 124.1
This proposed crossing is located at the bridge
over the Norfolk Southern Railroad and Route 615.
1-73 would cross under the Parkway here.
This area consists of a moderately steep
ridgeline containing a xeric (dry) pine~ak
forest. Dominant tree species include red oak,
white oak, Virginia pine, eastern hemlock,
mountain laurel and blueberry. Hurricane Hugo and
recent ice storrns have heavily impacted this
area. More than 70 percent of the canopy trees
have some ice damage to them. Botanically. this
is a unique area because it is recovering from
several "natural" disturbances. The
University of Tennessee has looked at this area
as part of a study involving patterns of
vegetation disturbance and recovery in the
southern Appalachians.
Part of the 1-73 corridor would run through the
28-acre t'Lipscomb" Tract which was acquired
by the Parkway during Summer 2000. The DEIS does
not show the new BRP boundary. We suspect that
more acreage would actually be taken from the
Parkway than the 3.37 acres listed in the DEIS.
This is one of the least preferred options from a
natural resource point of view because crossings
would result in extensive forest fragmentation
and loss of canopy vegetation. Secondary impacts
resulting from adjacent development along the new
interstate would result in still further impacts
to parkway resources.
From a natural resource perspective, this option
could heavily impact the Parkway. The forested
area is still relatively intact; a unique
situation since much of the Parkway in the
Roanoke Valley has been heavily fragmented by
development and roads. Extensive excavation would
be required that would greatly alter a unique
biological community. If this area becomes the
preferred alternative, a more comprehensive
biological survey of this area will be needed.
The DEIS should be revised to reflect the
additional acreage of NPS lands recently acquired
(Lipscomb Tract) that would be lost to 1-73 if
this option is selected. Also, the Parkway may
want to seek additional compensation (purchase of
additional land somewhere else, etc.) for any use
of the Lipscomb Tract. since the NPS has already
invested considerable time and money in the
acquisition of this tract.
Option 4, Segment 371, Milepost 126.5
This crossing is located 1/3 mile south of
Mason's Knob Overlook. Agricultural lease IN-104,
a small pasture lease. is located just to the
north of the proposed crossing. This site is a
mix of forest and small open farnil and.
Extensive removal of canopy vegetation would
likely be required. Several small strearns may
also be eliminated by this crossing. No
biological inventories have been conducted at
this site. This site is slightly more fragmented
than the previous site, primarily due to housing
developments being constructed nearby. Natural
resource information is generally lacking for
this site. We strongly recommend that a
biological survey of this area be conducted prior
to further consideration of this site as a
possible crossing.
This option is not preferred but would be
acceptable. This alternative would result in
moderate impacts to natural resources, but this
site is already somewhat impacted.
4.9 HISTORIC AND ARCHEOLOGICAL RESOURCES
4.9.1 ARCHITECTURAL RESOURCES
NPS reviewers agree with the Virginia Department
of Historic Resources determination that all
build alternative options involving the BRP will
use land from the Parkway, diminishing several
aspects of its integrity and that all options are
expected to have an adverse effect on the
Parkway.
4.10 PARKLAND CONSEQUENCES
4.10.2 Environmental Consequences
Agency reviewers note that until this point in
the DEIS there has been no discussion, or at
least no direct description of how each segment
of the build options would cross the Parkway as
under or overpasses. As described Options 2, 2a
and 2c (Segment 376) would cross over the
Parkway. This option has serious visual impact
implications for the Parkway foreground, middle
ground and cinematic experience in this view
area. Certainly, this proposed overpass is
problematic with respect to effective mitigating
measures. The U.S. Route 460 bridge overpass
utilized as a mitigation measure stone masonry
walls and arches to carry out the architectural
theme of stone masonry bridges utilized
throughout the Roanoke Valley. The discussion of
proximity of interchanges is not coupled with
statements about NPS concerns related to
additional secondary impacts caused by visible
interchanges. Potential impacts include night
light intrusion from lighted interchanges, scale
and mass of sound bar'riers, addition of lighted
signage in advance df interchanges, and potential
to cause land use changes adjacent to the
interchanges and beyond. All of these secondary
effects will need to be considered further prior
to VDOT selecting the preferred option to be
implemented. These are points of discussion to be
addressed during the requested on-site meeting.
4.12 SECONDARY AND CUMULATIVE IMPACTS
General Comment:
Text description and tables in this section do
not present. evaluate or compare secondary
impacts of 1-73 project option segments or
landscape units in terms of their potential
effect on the Blue Ridge Parkway's scenic view
areas. It describes land use change generally but
not specifically related to Parkway view areas or
the implications for crossings to lower Parkway
view area scenic quality. The 1-73 project is not
discussed cumulatively and in relation to
existing major crossings and other major highway
projects being proposed to cross the Parkway in
Virginia.
However, the DEIS implies that change is
inevitable so that a decline in the visual and
scenic quality of the BRP is inevitable.
In spite of this apparent assumption. there are
no maps included to show where the 28 percent of
the land that is already planned for conversion
from undeveloped to developed is located. This
data presented on a landscape unit scale would
certainly affect the NPS's evaluation and
preference towards crossing options. Again the
NPS requests that this data be presented at the
requested on-site meeting with the VDOT and
others.
4.13 SECTION 4(f)
4.13.1.2 Description of Section 4(f) Property
Table 4.134 lists overlooks that may be affected,
but it does not list or discuss non-overlook view
area vistas that have been identified throughout
the entire project area by the NPS. These
locations and the scenic quality ratings for
these view areas should have been an integral
part of the Section 4(f) Parkway discussion. View
area vistas are a maintained design element of
the Parkway just as are the overlooks. The
inventory and assessment of potential impacts
affecting view areas is important because not all
of the affected view areas are of the same scenic
quality, thus this be caused by the various
options.
4.13.1.5 Measures to Minimize Harm
The NPS wants to emphasize the importance of the
separate memorandum of agreement and the
commitment to working with the VDOT if a build
alternative is selected to minimize degradation
of resources and to maintain a quality visitor
experience of the Parkway. The identification of
design standards, final alignment location,
mitigating measures and management of Parkway
closures would be principle topic areas for
inclusion in the Memorandum of Agreement (MOA).
4.14 TEMPORARY EFFECTS DURING
CONSTRUCTION ACTIVITIES
General Comment
Given the nature of the build option crossings of
the Parkway with the construction of major bridge
structures either over or carrying the Parkway,
it would appear that the Parkway motor road would
need to be completely closed to traffic for some
length of time. Details related to closing the
Parkway and potential inconveniences for Parkway
visitors is a major concern of the NPS. The
details of roadway closure and detours are a key
area to be worked out between the VDOT and the
NPS.
4.15 RELATIONSHIP BETWEEN LOCAL
SHORT-TERM USES OF THE ENVIRONMENT AND THE
MAINTENANCE AND ENHANCEMENT OF LONG-TERM
PRODUCTIVITY
4.15.6 Aesthetics
The conclusion that construction of 1-73 would
not have a long-term visual impact on the BRP
because of mitigating measures and on-going
sub-urbanization seems to be missing the point.
If constructed. 1-73 would result in the
introduction of a major visual intrusion into
Parkway view areas. These view areas foreground
are now characterized by forested, rural or
suburban land uses. A four-lane highway being
constructed within any view area will
irretrievably affect its scenic quality
negatively and diminish the visitor experience
through that section of the Parkway. The tone of
this DEIS section minimizes the cumulative
impacts to Parkway resources arising from the
proposal and other changes. An MOA and a
cooperative effort in implementing mitigation
measures are critical to the overall success of
this project. Success for the NPS is based upon
providing visitors a scenic experience of viewing
undeveloped forest lands and rural landscapes.
SUMMARY of NPS CONCERNS
Before the VDOT selects a preferred corridor and
prepares the final EIS, the NPS has two concerns
to discuss with VDOT. The first concern is that
this document minimizes the level of detail in
the affected environment chapter and talks more
about process than description of the affected
environment, the issue being the absence of
substantive data to compare the merits of the
five option segments crossing the BRP or
impacting the Appalachian National Scenic Trail's
scenic viewshed. Secondly, inventory and impact
analysis data are generalized into segment or
option level of detail. However, for both the
Appalachian National Scenic Trail and the BRP,
specific landscape unit data are needed to
effectively evaluate build alternative options
and provide more meaningful comments to VDOT.
In summation, the NPS reviewers have a number of
concerns that are not adequately addressed in the
draft. Before the NPS will finalize its position.
the NPS requests that the VDOT schedule an
on-site meeting in Roanoke, Virginia with
Appalachian National Scenic Trail and BRP
planning staff and representatives of other
land-managing agencies charged with stewardship
of our Nation's parks and forests, the FHWA and
appropriate DEIS consultant staff. The meeting
purpose would be to review affected visual
environment and environmental consequences data
specific to the five segments and their
associated landscape units crossing the Parkway
and visible from the Appalachian National Scenic
Trail. This meeting should be scheduled as soon
as possible so that the concerns identified above
can be addressed in the final EIS.
Prior to attending the meeting Appalachian
National Scenic Trail and BRP staff would like to
receive copies of the Visual Quality and
Parklands Technical Memoranda prepared for this
project by members of the DEIS consultant team.
Also copies of proposed crossing visual
simulations or other graphic materials that
further illustrate build alternatives are also
requested. The DEIS referenced a FHWA publication
Visual Impact Assessment for Highway Proiects,
1981, and both the Appalachian Trail and Parkway
staff request that they be provided a copy each
of that manual for their use in reviewing the
DEIS. These technical documents would assist NPS
staff in further evaluating potential impacts and
making recommendations for preferences of the
five build crossings potentially affecting visual
resources.
Please schedule meetings with, and transmit
requested written and graphic materials to Don
Owen of the Appalachian National Scenic Trail, at
(304) 535-4003, and Gary Johnson of the BRP, at
(828) 271-4744; extension 210. Thank you for your
assistance in this matter and we look forward to
an early and productive meeting.
FISH AND WILDLIFE SERVICE (FWS) RESOURCES
Endangered Species Act Comments
The federally endangered Roanoke logperch
(Percina rex) is found throughout the Roanoke
River drainage basin in the project study area.
The federally endangered smooth coneflower
(Echinacea laevigata) is documented in the
project study area. The federally endangered
northeastern bulrush (Scirpus ancistrochaaetus)
and Indiana bat (Myotis sodalis) may also occur
in the project study area.
A species of freshwater mussel was recently
documented in the Dan River drainage in Stokes
County, North Carolina. At this time, the
taxonomic status of this mussel is undetermined
and DNA analysis is ongoing. It is possible that
this mussel is a federally listed species.
Therefore, the FWS will recommend that the
Federal Highway Administration and the VDOT
conduct surveys for this mussel for various
project alternatives within the Dan River
drainage.
The FWS recommends further coordination with FHWA
and VDOT to determine the extent of all
endangered species occurrence within the project
study area and specifically, along the corridor
of each project alternative. As the FWS stated in
its letter to FHWA dated September 12, 2000, the
FWS recommends a meeting with all interested
parties to discuss these listed species and the
need for surveys within the study area. This
meeting should include species experts, for the
species listed above, to discuss survey needs and
likely species occurrence within the study area.
The FWS notes that a Biological Assessment (BA)
has not yet been prepared for this project. The
BA should be included in the final EIS.
Guidelines for preparation of a BA were provided
by the FWS to the FHwA in its letter dated
September 12, 2000.
The FWS recommends that all survey results be
included in the BA that will be included in the
final EIS. In order to prevent any unnecessary
project delays, the FWS recommends that all
endangered species coordination be completed as
soon as possible. If the BA does not thoroughly
address the impacts of the various alternatives
on all federally listed species, the FWS may seek
referral of this project to the Council on
Environmental Quality pursuant to 40 CFR 1504.
Fish and Wildlife Coordination Act
Comments
The FWS is concerned about the large scale
impacts to forested habitat and farmland that are
likely to occur if this project is constructed.
All candidate build alternatives would adversely
impact thousands of acres of natural habitat and
fannnland. Such federally-funded habitat
destruction would have substantial negative
impacts on the fish and wildlife resources in the
construction area and wildlife-related
recreation. FWS notes that in 1996 for example,
77 million U.S. residents of age 16 and older
expended over 100 billion dollars on fishing,
hunting, and other fish and wildlife related
recreation (DOI - 1996). The FWS does not support
the expenditure of Federal funds that results in
unmitigated destruction of fish and wildlife
habitat.
The FWS recommends habitat
restoration/enhancernent, offsetting negative
impacts to fish and wildlife. as well as
wildlife-related recreation.
Habitat/riparian/floodplain
restoration/reforestation or establishment of
vegetated buffers along field edges are some of
many options that should be considered.
Literature Cited
The DOI, Fish and Wildlife Service and U.S.
Department of Commerce, Bureau of the Census.
1996 National Survey of Fishing, Hunting, and
Wildlife-Associated Recreation.
GEOLOGICAL/BIOLOGICAL RESOURCES:
Page 3.7-9, Chapter 3.0 AFFECTED ENVIRONMENT,
Section 3.7 Natural Resources,
Subsection 3.7.2.1 Forest Lands, Paragraph
3.7.2.1.5 Wildlife Species Associated with Forest
Habitat:
The report mentions white-tailed deer (Odocoile S
virginianus) as occurring in the proposed project
location. And, while some mitigation for wildlife
was suggested (page 4.7-3, Chapter 4.0
ENVIRONMENTAL CONSEQUENCES, Section 4.7 NATURAL
RESOURCES, Paragraph 4.7.3
Mitigation), nothing was said about preventing
white-tailed deer/vehicle collisions.
To address this issue, the U.S. Geological Survey
(USGS) recommends consideration of two current
research projects. Although the second project
focuses on mule deer (O.hemionus), the highway
behavior paflerns of the two deer species are
similar: Effectiveness of big game highway
crossing structures, and hierarchical approach
for studying mule deer behavior and habitat
relationships.
Descriptions of these projects can be accessed
from the USGS URL http://biology.usgs.gov, under
Current Projects, mule deer, or under Coop Units,
Utah Cooperative Fish and Wildlife Research Unit.
Research Projects, Mule deer.
We appreciate the opportunity to offer comments
on this project. For additional information
regarding park and recreation resources please
contact Don Owen of the Appalachian National
Scenic Trail at this number: (304) 535-4003, and
Gary Johnson of the BRP, at (828) 271-4744;
extension 210. For information regarding fish and
wildlife resources please contact Mr. William
Hester of the Virginia Field Office, FWS at (804)
693-6694; extension 134. For information on
geological/biological resources. please contact
Ms. Michalann Harthill (703) 648-4077, of the
U.S. Geological Survey.
Sincerely,
Willie R. Taylor
Director, Office of Environmental Policy and
Compliance
COMMONWEALTH of VlRGINIA
DEPARTMENT OF TRANSPORTATION
1401 EAST BROAD STREET
RICHMOND, 23219-2000
CHARLES D. NOTTINGHAM , COMMISSIONER
J. T. MILLS , STATE LOCATION AND DESIGN ENGINEER
February 23, 2001
Mr. Don Owen C/O ATPO
Harpers Ferry Center
Harpers Ferry, West Virginia 25425
Mr. Gary Johnson
Blue Ridge Parkway
199 Hemphill Knob Road
Asheville, North Carolina 28803
Dear Mr. Owen and Mr. Johnson:
We have received comments from the Department of
the Interior regarding the Draft Environmental
Impact Statement (DEIS) for the 1-73 Location
Corridor Study between Roanoke and the North
Carolina State Line. Included in these comments
were those from the Appalachian National Scenic
Trail and the Blue Ridge Parkway among other
interests.
After reading these comments it becarne very
evident that we should have provided both of
these groups with a copy of the Visual Quality
Technical Memorandum which has been prepared in
conjunction with the DEIS. This additional
information should enable you to better
understand how the specific findings were
developed.
We hope this document also will address the
concerns that have been raised in the Department
of the Interior's letter. If, following your
review of the Visual Quality Technical
Memorandum, you still feel a meeting will be
necessary, please contact Mr. Mark Wittkofski, in
our Environmental Division at (804) 371-6867) or
myself at (804) 786-2566 and we will try to set
one up towards the middle of March to discuss
your concerns further.
We appreciate your thorough review of the
documentation leading up to the publication of
the DEIS and hope that this supplemental
information will serve to further enhance your
understanding of the reasoning of the findings
and conclusions in the DEIS. We regret that this
information had not been provided with the DEIS,
and apologize for any inconvenience that the
additional review time required for this material
may cause. We look forward to your comments and
as stated above we will be more than glad to meet
to discuss this additional information.
Thank you again for your review of this material
and your continued interest in this most
important highway project.
Sincerely,
Patsy Napier
Transportation Engineer
Program Manager
Cc:
Mr. Roberto Fonseca-Martinez
Mr. Ed Sundra
Mr. Fred Altizer
Mr. Earl T. Robb
Mr. Calvin Boles
WE KEEP VIRGINIA MOVING
L3027
March 13, 2001
Mn Earl T. Robb
State Environmental Administrator
Virginia Department of Transportation
1401 East Broad Street
Richmond, Virginia 23219-2000
Dear Mr. Robb:
We have received and reviewed the Visual Quality
Technical Memorandum for the 1-73 Location Study
Between Roanoke and the North Carolina State
Line, Corrrrnonwealth of Virginia Draff
Environmental Impact Statement (DElS) and Draft
Section 4(f) Evaluation-FHWA-VA- EIS-NH-962-2
(004), State Project: 0073-962-F01, PE101. We
appreciate the opportunity to review the visual
inventory and analysis data included in the
technical memorandum.
The memorandum provided the visual quality data
required for us to better understand the five
proposed build alternatives. Based upon our
review, we agree with the stated effects on the
Blue Ridge Parkway for segments 371 (build
options 4) and 372 (build options 1 and 1a).
These two segments and associated build options
located at Milepost 126.5 and 103.6 have the
maximum potential for visibility from the Parkway
motor road vistas and paved parking overlooks.
Visual impacts would be substantially adverse for
both of these two segments. The National Park
Service (NPS) continues to find these two
segments the least preferred of the proposed
Parkway crossings. This conclusion is based on
the Service's understanding of the potential for
visual quality and natural resource impacts
resulting from either segment crossing.
Segment 118C at Milepost 121.4, included in build
options 2b, 3, 3b and 3c continues to be the most
preferred crossing of the Blue Ridge Parkway.
From the visual quality and natural resource data
provided, NPS reviewers find that constructing an
interstate highway within the existing U.S. Route
220 is the most preferred crossing option.
Segment 105 at Milepost 124.1 is the next most
preferred crossing from the potential for visual
resource impacts. However, this crossing would
result in extensive forest fragmentation and loss
of canopy vegetation and is one of the least
preferred crossings based upon natural resource
impacts. If this option is selected then agreeing
on mitigating measures will be critical.
Segment 376 located at Milepost 116.9 is included
in build options 2, 2a, and 2c. According to the
technical memorandum analysis this crossing
provides the lowest visibility from the Blue
Ridge Parkway and would have the least effect on
visual quality. However, in the draft
environmental impact statement this segment is
described as an overpass crossing which seems to
be directly contradicting the visual analysis
effect finding.
Review of the technical memorandum did not
resolve two issues-1. Conflicting visual analysis
data and proposed overpass crossing of segment
376, and 2. Visual impact score of
"none" for segments 118C and 371. While
the technical memorandum data is helpful, we
respectively request a meeting on-site to review
the crossing details to obtain answers to the
above questions. After the meeting, Blue Ridge
Parkway management will provide you with a
prioritized list of most to least preferred
crossings.
By copy of this memorandum we are requesting that
Mr. Mark Wittkofski in VDQT's Environmental
Division arrange an on-site meeting in Roanoke
for April 4th or 5th This request is in
accordance with Patsy Napier, VDOT Program
Manager letter dated February 23, 2001. Please
advise Mr. Gary Johnson, Chief Resource Planning
and Professional Services Division of the
scheduled meeting date at (828) 271-4744 or
e-mail gary_w_Johnson@nps.gov.
Thank you for providing us the technical
memorandum. It was very helpful. We look forward
to further discussions about the 1-73 alternative
build options.
Sincerely
Daniel W. Brown
Superintendent
cc:
Mr. Don Owen c/o ATPO
Harpers Ferry Center
Harpers Ferry, WV 25425
Mr. Roberto Fonseca-Martinez
Division Administrator
Federal Highway Administration
P.O. Box 10249
400 N. 8th Street Rm. 750
Richmond, VA 23240
Mr. C. F. Boles
Assistant Division Administrator
Virginia Department of Transportation
1401 East Broad Street
Richmond, VA 23219
Mr. Fred Altizer
District Administrator
Virginia Department of Transportation
P.O. Box 3071
Salem, VA 24153
Mr. Mark Wittkofski
Environmental Division
Virginia Department of Transportation
1401 East Broad Street
Richmond, VA 23219
Gjohnson:bk:3/13/01:271-4770x210
L3027
April 12, 2001
Mr, Roberto Fonseca-Martinez
Division Administrator
Federal Highway Administration
Post Office Box 10249
400 North 8th Street, Room 750
Richmond, Virginia 23240
Dear Mr. Fonseca-Martinez:
We have reviewed the 1-73 Location Study Between
Roanoke and the North Carolina State Line
Commonwealth of Virginia Draft Environmental
Impact Statement (DEIS) and Draft Section 4(f)
Evaluation FHWA-VA-EIS-NH-962-2, State Project:
0073-962-f01,PE 101; Visual Quality Technical
Memorandum, October 2000; and 1-73 Location
Study. In addition to reviewing the referenced
documents, Gary Johnson, Chief Resource Planning
and Professional Services Division, met with
Virginia Department of Transportation (VDOT) and
project consultant staffs in Roanoke, Virginia on
April 5, 2001 to discuss the five build option
segments that may potentially cross the Blue
Ridge Parkway. The meeting was most informative
and we appreciate the opportunity to directly
discuss Segments 105, 118C, 371, 372, and 376
with VDOT and consulting staffs.
Based upon review of pertinent documents and our
discussions, Parkway staff and management offer
the following preferences and conclusions on
potential 1-73 crossings of the Parkway.
Most Preferred Crossing - The
National Park Service's most preferred crossing
of the Blue Ridge Parkway is segment 118C,
Milepost 121.4 included in Build Alternative
Options 2b, 3, 3b, and 3c. This is the existing
four-lane corridor of U.S. Route 220, a major
transportation corridor that has been a part of
the Parkway visitor driving experience since the
Parkway was constructed through the Roanoke
Valley during the late 1950's and early 1960's.
Widening of the U.S, 220 corridor to accommodate
1-73 will further impact this area of the
Parkway, but the landscape changes would be more
consistent with existing land use than they would
be in the other four proposed Parkway crossing
locations. Mitigating measures should insure that
vegetation that currently screens the Rocky Dale
Quarry from the Parkway is left intact.
Despite the fact that this alternative would
require the most land from the Parkway, this is
the preferred build option from a natural
resources perspective because it uses an already
heavily disturbed area- the existing U.S. Route
220 corridor.
However this crossing would eliminate the
existing Parkway interchange with U.S. 220 and
the options for providing a connection between
1-73 and the Parkway are less-than satisfactory.
As you know Parkway planning staft VDOT and
consulting staff all have studied possible
connections. To date all of the studied routes
would require visitors exiting 1-73 to follow
frontage roads, two other city streets and then
finally connect with the Parkway motor road via
Mill Mountain Spur Road. Finding a more direct
connection while maintaining ample driving time
to transition from an interstate highway to the
Parkway is a major concern to us. Mso the
difficulty of way finding for travelers is a
concern. The scenic quality of the route is a
very important factor for the route as well.
Second Most Preferred Crossing -Segment
376, Milepost 116.9 is in a section of Parkway
dominated by rural farm and residential use. This
portion of Parkway lies midway between U.S. Route
24 and U.S. Route 220. Views of major road
corridors in this area and within Parkway view
areas are inconsequential. The narrow secondary
routes that cross the Parkway do so under or over
the Parkway on picturesque stone arch bridges.
These structures are so well placed and their
scale is such that they enhance the overall
driving experience and do not dominate it.
An interstate highway constructed to underpass
the Parkway through this area with its scale,
mass and engineered character could overpower the
current landscape setting. But after fiarther
study by our Resource Planning staff, we believe
that an alignment carried across the Parkway on
an overpass has great merit and it is our second
most preferred crossing. The Parkway, as it comes
out of the forest from the north and enters this
rural landscape setting, passes through a cut
section where the topography rises above the
motor road on both sides. This area with some
additional earthwork-fill offers an opportunity
to create a crossing that could follow the
existing landform pattern thus lying more gently
on the landscape. By crossing the Parkway
overhead much of the interstate alignment would
not be visible to the Parkway traveler because
they would be below the grade-separated structure
and cut slopes. Placement of trees and shrubs
along the interstate corridor would flirther
soften and screen the four-lane corridor from
view. Please see the three-page enclosure that
graphically illustrates our thoughts on this
overpass crossing.
This segment would cross through four
agricultural leases one of which has a small
wetland area. In addition just north of milepost
117, there is a rich cove forest where there are
numerous large diameter oaks and maples. This
option is not the most preferred from a natural
resource perspective but would be acceptable
because resources are already somewhat
fragmented. If this build option is selected a
more in depth and comprehensive biological survey
would be required to address mitigating measures.
Noise, land use changes, and view area scenic
quality impacts are of great concern in this
location and degree of impacts would be directly
proportional to the alignment location scale of
cuts and fills, and mitigating measures such as
the placement of vegetation to buffer the road
corridor.
Third Most Preferred Crossing-
After reviewing all available materials and
including staff input, we now rank Segment 105,
Milepost 124.1 included in Build Alternative
Option 3a as our third most preferred crossing
location. This ranking is based upon our
understanding of potential visual and natural
resources impacts and consistency of the visitor
experience through this section of Parkway
perspective. Between Parkway Milepost 121.4 at
U.S. Route 220 and Milepost 126.1 there are four
Virginia Secondary Route underpass crossings of
the Parkway. Proposed Segment 105 is located
between the existing underpass crossings of VA
Route 615 and the Norfolk Southern Railroad and
VA Route 613. This series of underpass structures
are a primary character-defining element of this
4.7-mile section of Parkway. While construction
of a new corridor with side-hill cuts to
accommodate a four-lane interstate would
dramatically change the landscape, the crossing
of another road corridor would be more consistent
with the existing visitor's experience of
encountering a series of roads over passed by the
Parkway motor road. Existing land uses and site
conditions made visible by this underpass
crossing would be more consistent with the
current experience here than at the other three
locations which are characterized by forest
covered slopes or rolling rural residential and
farmlands.
From a natural resources perspective, this is a
less preferred option than Segments 118C and 376
because crossing here would result in extensive
forest fragmentation and loss of canopy
vegetation. In our review of the visual
simulation for this crossing the extent of forest
cover being removed is very obvious. If this
option were selected, planting cut slopes would
be an important and necessary mitigation to be
applied here.
Least Preferred Crossings - Two
of the remaining three segments--Segment 371,
Milepost 126.5, and Segment 372, Milepost 103.6
included in Build Alternative Options 4; and 1
and 1a, respectively are grouped together as the
Service's least preferred of the proposed
crossings. The construction of an interstate
highway in both of these Parkway landscape
settings would dramatically change the existing
view area scenic quality, and land uses, all of
which are absent of major roads seen from or
crossing the Parkway. Increases in highway noise
generated by interstate highway traffic volumes
and vehicle speed would radically alter existing
site noise conditions
Segment 371, Milepost 126.5 is the southernmost
proposed segment, characterized by forest cover
and is just south of Masons Knob Parking
Overlook, a paved parking area for 28 cars. Both
the existing land use and the proximity of
Segment 371 to a formal overlook parking area are
of great concern to the NPS. Noise increases,
land use changes and view area scenic quality
impacts form the basis for this being a least
preferred crossing option. This build option
would result in moderate impacts to natural
resources, but the site is already somewhat
impacted, so while it is not preferred this would
be an acceptable option.
Segment 372, Milepost 103.6 is the northernmost
proposed crossing of the Parkway. Between Parkway
Milepost 90 and 104 the Parkway traverses
primarily National Forest land and the visitor
experience is dominated by a forested road
corridor with vistas of undeveloped forestlands.
From Milepost 104 to 105.8 land use is rural
residential with U.S.460 crossing the Parkway at
Milepost 105.8. The introduction of another
four-lane highway, especially one meeting
interstate standards, into this forest dominated
setting greatly alters the existing visitor
experience. Again increased noise, changes in
land use and view area scenic quality impacts
form the basis for this being a least preferred
crossing option. From a natural resources
perspective this is one of the least preferred
options because there would be extensive forest
fragmentation.
Again, we want to emphasize the importance of a
separate memorandum of agreement (MOA) and our
commitment to working with the Federal Highway
Administration and VDOT if a build alternative is
selected. Our goal is to minimize the degradation
and long-term impairment of Parkway resources and
to maintain a quality visitor experience for
Parkway travelers. The identification of design
standards, final alignment location, mitigating
measures and management of Parkway closures would
be principle topics for inclusion in the MOA.
We understand that for you and us this is a long
and tedious undertaking. Both FHWA and VDOT
continue to meet our requests for information and
discussion on this project and it is very much
appreciated. If this project comes to fruition,
it will take cooperation by all parties involved
to meet the numerous goals and needs that we each
have. Mr. Gary Johnson will continue to
coordinate this project for the Parkway and he
can be reached by telephone at 828/271-4744 ext.
210 to discuss this letter as needed.
Sincerely,
(SGN) JOSEPH W. AULL
Daniel W. Brown Superintendent
Enclosure
cc:
Plateau District Ranger w/enclosure
Plateau District Facility Manager w/enclosure
Mr. Willie R. Taylor w/enclosure
Director, Office of Environmental Policy and
Compliance
United States Department of the Interior
Office of the Secretary
Washington, D.C. 20240
Ms. Pam Underhill
Park Manager
Appalachian National Scenic Trail
Harpers Ferry Center
Harpers Ferrv, West Virginia 25425
Mr. C. F. Boles, III w/enclosure
Assistant Division Administrator
Virginia Department of Transportation
1401 East Broad Street
Richmond, Virginia 23219-2000
Mr. Earl T. Robb wlenclosure
State Environmental Administrator
Virginia Department of Transportation
1401 East Broad Street
Richmond, Virginia 23219-2000
Mr. Fred Altizer
District Administrator
Virginia Department of Transportation
P.O. Box 3071
Salem, Virginia 24153
Gjohnson:bk.4/12/01 :271-4779xl10
Overpass
Study Concept Pictures



|