Blue Ridge Environmental Defense League
BREDL TRANSPORTATION AND LAND USE


Army Corps of Engineers comments on I-73 DEIS

Jan. 5, 2001 - Army Corps requests comment extension

Jan. 8, 2001 - VDOT denies request

Feb. 1, 2001 - Army Corps of Engineers comments on DEIS


DEPARTMENT OF THE ARMY
NORFOLK DISTRICT, CORPS OF ENGINEERS
FORT NORFOLK, 803 FRONT STREET
NORFOLK, VIRGINIA 23510-1096

REPLY TO
ATTENTION OF:

January 5, 2001

Eastern Virginia Regulatory Section


Mr. Earl T. Robb
Environmental Engineer
Virginia Department of Transportation
1401 East Broad Street
Richmond, Virginia 23219

Dear Mr. Robb:

This is in reference to the Draft Environmental Impact Statement (DEIS) prepared by the Virginia Department of Transportation (VDOT) and the Federal Highway Administration for the proposed I-73 project. The Norfolk District of the Corps of Engineers is a cooperating agency in the development of the document for this project. The transmittal letter attached to the document indicated that comments should be submitted by January 12, 2001.

Due to the high volume of VDOT projects under review in our office at this time (including several VDOT has indicated are of very high priority, such as the Rt. 288 projects), the complexity of the I-73 project and the length of the document, it will be very difficult for us to meet that deadline. Therefore, as a cooperating agency, we are requesting an extension until January 22, 2001 to submit our comments on the DEIS.

We appreciate your assistance in this matter, and we would appreciate a telephone call from your staff as soon as possible to let us know your decision. Should you have any questions, you may call Alice Allen-Grimes at (757) 441-7219.

Sincerely,



Nicholas L. Konchuba
Chief, Eastern Virginia
Regulatory Branch


Copy Furnished:

Federal Highway Administration, Richmond

CF: READING, FILE


COMMONWEALTH of VIRGINIA
DEPARTMENT OF TRANSPORTATiON
1401 EAST BROAD STREET
RICHMOND. 23219-2OOO


CHARLES D. NOTTINGHAM
COMMISSIONER

EARL T. ROBB
STATE ENVIRONMENTAL ADMINISTRATOR



January 8, 2001




Mr. Nicholas L. Konchuba
Ch let Eastern Virginia Regulatory Section
U.S. Corps of Engineers
Fort Norfolk, 803 Front Street
Norfolk, VA 23510-1096

Dear Mr. Konchuba:

This letter is in response to your letter of January 5, 2001, requesting additional time for providing comments of the Draft EIS for the Interstate 73 Corridor Location Study. As you know, the FHWA distributed the Preliminary DEIS to the cooperating agencies on July 21, 2000. Given your agency's comments to the Preliminary DEIS, we have a sense of your concerns and interests in the project.

Because of the project's high level of public interest and in order to maintain the project development schedule, we established a finite period for public comments. The final date for submission of comments on the DEIS is January 12, 2001. This date represents a 62-day cumulative period following the publication of the notice of the document's availability in the Federal Register.

The Department, however, remains hopeful that your agency will provide to us your comments. We would like to receive them as soon as they can be completed. I trust you will be able to send them before we finish the analysis of the public comments and make our presentation to the Commonwealth Transportation Board.

Please do not hesitate to contact me at (804) 786-4559, should you have any additional questions.

Sincerely,


Eart T. Robb
State Enviornmental Administrator
cc: Mr. Roberto Fonseca-Martinez
Mr. Edward Sundra
Mrs. Patsy G. Napier


WE KEEP VIRGINIA MOVING


DEPARTMENT OF THE ARMY
NORFOLK DISTRICT, CORPS OF ENGINEERS
FORT NORFOLK. 803 FRONT STREET
NORFOLK. VIRGINIA 23510-1096

February 1, 2001

REPLY TO
ATTENTION OF:

Eastern Virginia Regulatory Section
98-4506-15


Mr. Roberto Fonseca-Martinez
Division Administrator
Federal Highway Administration
Dale Building
1504 Santa Rosa Road
Richmond, Virginia 23229

Dear Mr. Fonseca-Martinez:

This letter provides the comments of the Norfolk District Corps of Engineers on the Draft Environmental Impact Statement (DEIS) prepared for the proposed Interstate 73 (I-73) in the vicinity of the City of Roanoke, Virginia and south to the North Carolina line. The Federal Highway Administration (FHWA) and the Virginia Department of Transportation (VDOT) are preparing the EIS, and the Corps of Engineers is a cooperating agency in the preparation of documents for this project. In that role, we reviewed the pre-DEIS provided our comments on that document in a letter dated September 1, 2000. Those comments focused on the content of the document and the way the information was presented. Our comments on the DEIS focus on both the document and the project itself, considering the relative merits of the various alternatives presented in the DEIS.

Our primary concern with the pre-DEIS, as stated in our letter at that time, was the lack of documentation of the need for an interstate facility. As we noted, the problems establishing the need for improvements in the Route 220 corridor are provided and discussed, and additional information has been added to the DEIS to clarify the reasons that FHWA has determined that only an interstate-level facility will address the Purpose and Need, summarized on page 1-5. The Virginia portion of I-73 is seen as one segment of an interstate highway to extend from Michigan to South Carolina. Information is provided in support of the position that an interstate-level facility will better facilitate regional economic growth than another type of highway facility. The DEIS also identifies the movement of freight and vehicles and the enhancement of "general mobility and transportation linkage" through the Michigan to South Carolina "target market." These needs from Michigan to South Carolina are not supported in the document, but simply stated as goals of I-73. The information in support of the need for an interstate-level facility focuses primarily on what "Congress intended" in the National Highway Designation Act of 1995, TEA-21, and ISTEA with reference to I-73.

It is stated on page 2-6 that "FHWA believes that the designation by Congress of 'I-73' indicates the Congressional intent that this route would be an Interstate highway . . ." Yet, the pre-DEIS indicated that Ohio is not considering construction of I-73 (due to funding problems), and West Virginia has completed a Final EIS to upgrade an existing highway, but not to interstate standards. We note that this information was not included in the DEIS. Apparently the need for an interstate facility from Michigan to South Carolina is not apparent in certain other states along the corridor. As we noted in our comments on the pre-DEIS, if a segment of an interstate facility is constructed in Virginia, it appears that it will not be part of a larger whole. With that framework, the substantiation of the needs in the Michigan to South Carolina corridor that can only be addressed by an interstate appears to be undermined.

Based on the information in the DEIS, it is not clear that a non-interstate build alternative would not address the substantiated problems identified in the Purpose and Need while at the same time potentially reducing impacts to waters of the U.S. A Department of the Army permit will be required for the construction of a build alternative or the TSM alternative, since all of these alternatives involve the placement of fill in waters of the united States, including wetlands and navigable waters. As part of our public interest review and in accordance with the Clean Water Act Section 404(b) (1) Guidelines, the Corps must evaluate alternatives that avoid impacts to waters of the U.S. Because an upgrade of Route 220 was not included in the DEIS, it appears that all reasonable and feasible alternatives to minimize environmental impacts have not been evaluated. Our dilemma is that we do not know whether an improvement of Route 220 will minimize impacts. Therefore, the information would be required for us to evaluate a permit application for this project.

All of the Build Alternatives will result in substantial environmental impacts: the displacement of 340 to 707 homes and 23 to 63 businesses; 2014 to 4391 acres of forests; 12 to 36 acres of wetlands; 76 to 166 stream crossings; noise increases of 10 dBA or greater to 411 to 3316 homes; etc. The impacts were estimated based on a 600-foot wide corridor, whereas the typical section involves a 250-foot right-of-way. The broad corridor used for estimating impacts complicates our evaluation of the relative merits of one alternative versus another, since it is unknown to what extent shifts within that corridor will reduce impacts. However, based on the information as presented, we have some recommendations.

Alternatives that avoid impacts to waters of the U. S., including wetlands, are preferred. Based on the information in the DEIS, Alternatives 3 (3, 32, 3b, and 3c) and 4 involve fewer crossings of streams. The "3' Alternatives also involve the least impacts to wetlands. However, it is unknown whether through bridging and alignment shifts the impacts of the various alternatives could be made approximately equivalent in terms of impacts to waters and wetlands.

An important consideration in our evaluation of the alternatives is the potential for secondary impacts resulting from development stimulated by the project. The DEIS evaluates potential impacts from development by determining the amount of developable land located within a one-mile radius around each interchange along each Build Alternative, since interchanges are generally the most likely location for such development to occur. Developable land was defined as all agricultural and forest land not considered prime agricultural property or designated as wetlands (Table 4.12-1, page 4.12-2). The document states that 24-39% of this land is already planned for conversion to developed land, and suggests that development is already anticipated in these areas with or without the introduction of an interstate.

This information and analysis raises two issues we consider important: (1) As noted at several locations in the document, I-73 is included in most local and regional plans. Therefore, the planned conversion of lands may very well be an indication not that the development will occur regardless of the interstate, but rather that the interstate is already expected and development plans have already been spurred by that expectation. A statement to that effect should be added to the Final EIS; (2) At interchanges of the various alternatives, 61-76% of the land which is developable is not already planned for development, but will likely become attractive for development if an interstate is constructed. This analysis suggests a likelihood of considerable secondary development resulting from the roadway. It is noted on page 4.12-3 that less than one percent of the amount of acreage at the interchanges represents wetlands under any of the build options. However, Table 4.12-1 indicates that all of the "2" and "3" alternatives include 164-176 acres of wetlands within the interchange radii. While these areas would be subject to regulation, we have concerns that the construction of the interstate will increase pressure on and impacts to these wetlands. Avoidance of potential secondary impacts to wetlands, as well as direct impacts, should be a factor in your selection of an alternative.

To summarize, our primary concern with the DEIS is that it is unknown whether impacts to communities and natural resources could be reduced through the construction of a build alternative of a lesser design than an interstate. At the same time, the DEIS does not substantiate that only an interstate-level facility will address the Purpose and Need, other than an interpretation of the "intent" of Congress. We prefer alternatives that avoid impacts to waters of the U.S., recognizing that other factors must be considered in determining whether an alternative is practicable. Both direct and indirect/secondary impacts to waters of the U.S., including wetlands, are being considered in our comparison of the alternatives. The Final EIS should document how avoidance and minimization of impacts to waters of the U. S. was a factor in the selection of an alternative.

Please see the enclosure for additional, specific comments we have concerning the DEIS. As a cooperating agency, we appreciated the opportunity to review and comment on the pre-DEIS as well as the DEIS. We trust that our comments and recommendations will be fully addressed, with a goal of the Corps being able to adopt the EIS prepared by FHWA as part of our compliance with the National Environmental Policy Act.

Should you have any questions, you may contact Alice Allen-Grimes at 757-441-7219.

Sincerely,

J. Robert Hume, III
Chief, Regulatory Branch

Page-Specific Comments of the Corps of Engineers
Draft Environmental Impact Statement, I-73


1. Page 3.7-1. While it is likely that the I-73 project will be coordinated through VDOT's monthly interagency coordination meeting, permits will probably not be "issued" at the meeting, as suggested on this page. For a project of this size, a public notice would likely be issued, after which a permit decision (issuance or denial) would be made, considering public comments.

2. Page 4.1-2, Table 4.1-1. Is there an error in the ADT volume for Option 4 for the segment of Rt. 220 north of Ridgeway? That segment is the same for Option 2 (2, 2a, 2b, 2c), and yet the volumes shown for Option 4 are twice the volumes for Option 2. Options 2 and 4 share the same location south of Ridgeway too, so it is not clear why there is a jump in volumes for Option 4 north of Ridgeway.

3. Page 4.1-12, Travel Time Analysis. It is stated that the travel time analysis under the Build condition assumes a completed I-73 from Michigan to Charleston, SC. West Virginia has completed an EIS to improve an existing highway to less-than-interstate standards and Ohio is not pursuing an I-73 project due to funding problems. Therefore, the Travel Time Analysis seems to be predicated on a situation that will not occur, estimating improvements that are unsubstantiated.

4. Page 4.1-13. Table 4.1-10. The travel time savings within Virginia --five minutes from Roanoke to Martinsville, 3 minutes from Roanoke to Rocky Mount, and 6 minutes from Roanoke to Smith Mountain Lake - seem limited when the substantial impacts associated with the project are taken into consideration.

5. Page 4.2-16, Table 4.2-7. It is not clear what is intended by the column "Tourist Attractions." The narrative that precedes and refers to the table discusses only the "Enterprise Zones and Growth Areas," but does not discuss the tourist attractions. Are the tourist attractions located within a certain distance from the various options? If so, is the implication that there is better access to them or potential negative impacts because interchanges are not located near these tourist attractions? The purpose for including the information should be explained.

6. Page 4.7-3, Section 4.7.1.3. The text on the previous page acknowledges that a new interstate will serve as a physical barrier to wildlife species and that wildlife-vehicle collisions will increase. However, in the discussion of mitigation in this section, no mention is made of providing wildlife crossings. For a project of this size, with the potential for significant interruption of wildlife corridors, the feasibility and potential effectiveness of providing crossings for wildlife should be evaluated.

7. 4.7-6. Section 4.7.2.3. The discussion of mitigation for impacts to aquatic habitat simply states that "compensation measures for unavoidable impacts will be developed during the permit process." It is important in evaluating the comparative merits of the alternatives to know the potential opportunities for compensating for such impacts. While it is recognized that the type and location of impacts is different for the alternatives, for a project of this size with a potential for such substantial impacts, efforts should be underway now to develop a conceptual compensation plan. Such a plan would consider appropriate goals for compensation, the type of compensation, and potential sites. For example, it is difficult to identify suitable sites for stream mitigation, whether through restoration of riffles/pools, provision of buffers, limiting access by cattle (fencing), or whatever. The project proponents should invest time now to find such opportunities. To begin the effort, the project proponents could investigate stream improvement opportunities on publicly held land in the study area.

8. Page 4.7-7, Section 4.7.3. With reference to navigable waters, it is stated for both the TSM and build options that temporary causeways and cofferdams will be used for bridge construction. Such temporary features in the navigable waters will have to be coordinated and approved with reference to their potential impacts to navigation as well as water quality issues. Causeways should not extend more than 50% across a waterway at any one time, and signage or other warnings to boaters may be required. Bridge heights should be coordinated prior to design.

9. Page 4.7-10, Section 4.7.3.2. The DEIS states that ponds formed through impoundment of "ephemeral streams" were determined to be non-jurisdictional. It is difficult to distinguish between and intermittent stream and an ephemeral stream, and ponds formed through the impoundment of intermittent streams are jurisdictional. Please have any determination that a stream is ephemeral confirmed by the Corps of Engineers.

10. Page 4.7-12, Table 4.7-4. The wetland impact estimates for several of the build options have changed substantially since the pre-DEIS. Those associated with Options 2b, 2c, 3, 3a, 3b, and 3c have all increased, some by as much as 20 acres. What led to those changes? We also noted that the impacts for the TSM alternative have dropped 27 acres from the pre-DEIS. We noted in our comments on the pre-DEIS that those impacts seemed very high, but we would like to know the reason for the change in number

11. Page 4.7-14, section 4.7.3.2.3. This section discusses mitigation for impacts to wetlands. As we advised above for other aquatic resources, the project proponents should at this time be actively working to identify potential wetland compensation sites. The opportunity for providing wetland compensation for the various alternatives is an important consideration in comparing them. It is stated that compensation for some of the impacts to ponds could be provided through the inclusion of extended wet detention basins as part of the stormwater management (SWM) system. The requirement to provide SWM is above and beyond mitigation for aquatic resources, and SWM facilities by themselves are generally not accepted to "double" as mitigation. The text also includes preservation of existing wetlands as an option for mitigation. If preservation were proposed as mitigation, then the project proponents should identify threats to any properties proposed for preservation. In addition, if preservation is included as a component of any mitigation package, a minimum of 1:1 replacement of wetlands through restoration or creation is generally required in addition to any preservation to guarantee no net loss of wetland functions and values.

12. Page 4.12-3. As we noted in our letter, it might or might not be true that development that is already planned in the proposed interchange locations means that development will occur with or without the interstate facility. Clearly, the interstate is anticipated by all of the localities and has been considered in their planning. The planned development could very well be because the interstate is expected and not regardless of it. A statement to that effect should be added to the Final EIS.

13. Section 4.13. There is no mention of historic architectural structures in the 4(f) discussion. It is our understanding that Section 106 properties are also Section 4(f) properties. Archaeological properties are discussed, along with the Blue Ridge Parkway (included as a parkland) . Section 4.9.1 on page 4.9-1 states that located within the Area of Potential Effect of the build options are 14 architectural resources eligible for the National Register. Are they not included within the Section 4(f) analysis because there is no expected "use" of these properties? This section should discuss architectural resources, even if only to state why they are not being included as potential Section 4(f) properties.

Enclosure

Copies Furnished:

Virginia Department of Transportation, Richmond
Environmental Protection Agency, Reston
U.S. Fish and Wildlife Service, Gloucester
National Marine Fisheries Service, Oxford
Virginia Department of Environmental Quality/Water Division, Richmond

CF: READING, FILE